CITY OF SWISHER

SEWER PERMIT APPLICATION

                                                                                               

A.                 Sewer Application:

 

1.                  Application – Any person desiring to make a connection with the sewer system shall first file with the clerk an application within 30 days of required service.

2.                  Permit Fee - $2,000 payable to the City of Swisher when application is received.

3.                  Bond Required – The person performing the connection shall provide a surety bond in the sum of $1,000.  Submit this bond when permit is returned to the City Hall requesting inspection.

4.                  Plumber Required – Any connection to a public sewer shall be made by a plumber approved by the City.

5.                  All work will be done by City Ordinance.

6.                  Inspection Required – All connections with the sanitary sewer system before being covered shall be inspected and approved in writing.  Return sewer application with top portion completed, map drawing location of sewer connection, at this time City Clerk will contact the City Inspector.

7.                  Sewer rental fee starts when connection is made.

 

B.                 Violation and Penalty:

 

            Any person, firm or corporation who violates, disobeys, omits, neglects, or refuses to comply with, or who resists the enforcement of any of the provisions of this Ordinance shall, upon conviction, be fined not more than One Hundred Dollars ($100.00) for each offense.  Each day that a violation is permitted to exist shall constitute a separate offense.

 

Building/Sewer Permit Instr.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

CITY OF SWISHER, IA

 

APPLICATION AND PERMIT FOR SEWER SERVICE

 

                                                          PERMIT NO. _________________

 

Application is hereby made for authority to connect the premises at:

          ___________________________________ Street, Ave.

          ___________________________________ Subdivision/Addition

          ___________________________________ Lot Number

with the town’s sewer main on ________________________Street, Ave., by a _______ inch V.C.P., or C.I. Soil Pipe.  Connection will be made __________________ feet North, South, East, West of the manhole located at the intersection of ___________________ and ____________________.  All material and workmanship will be in strict compliance with Town Ordinances relative to such work and shall be approved by the Citys Inspector before backfilling.

 

____________________________  ____________________________

    Owner or Authorized Plumber                           City Clerk

 

RECORD OF SEWER TAPS (to be completed by City Inspector)

 

          ______________________________ Street, Ave.

          ______________________________ Subdivision/Addition

          ______________________________ Lot Number

 

OWNER/BUILDER ___________________________

SIZE OF PIPE ______________________ KIND _________________ LOCATION OF TAP ___________________________________________

___________ FEET FROM ______________________________________ LINE OF ______________________________________________STREET

DEPT OF MAIN SEWER _____________________________________FT.

ENTERS LOT AT ___________________________________________FT.

FROM _________________________ LINE OF ___________________ST.

DEPTH OF PROPERTY LINE _________________________________FT.

PLUMBER _________________________________

REMARKS_________________________________________________________________________________________________________________

 

_____________________________     ______________________________

                      DATE                                               INSPECTOR

 

Application Fee Pd. ______________________Amount / Date_________